The Resurrection of Adamsville’s Mill Pond
By
Jon Alden
Everythingwestport.com
March
1, 2008

As far as mill locations go, the spot
on which Gray’s Grist Mill currently resides is surely one of the oldest sites
still operating in North America. The first mill was constructed in the early
17th century.
Ralph Guild is Chairman of the Board for
Interep, the largest independent national sales and marketing organization
specializing in radio, the Internet and new media. He has homes in New York and
in Acoaxet.
Ralph first
heard in the late 70’s that the Gray’s Grist Mill and Adamsville Pond property
was up for sale. Fearful of a change in its use, he purchased the property in
1980, insuring then current owner, John Hart, with a handshake that he would
preserve and continue to operate the grist mill. Ralph was true to his word.
Much work was done to restore the mill with the help of
restoration expert Pete Baker among others. Now attention was
turned to the ailing Adamsville Pond. Years of silt and sediment accretion of
up to 18 to 24” accompanied by increased aquatic plant growth had reduced the
overall water surface by 60% as compared to photos taken in 1929! The pond’s capacity
to effectively operate the mill was greatly reduced. Ralph and members of the
local community wanted the pond back to the way they remembered it as youths.
Dredging and habitat restoration was the only answer.
Left: Pond, dam and stone fish ladder
fully restored - March 8, 2008.
However, many
complications would be encountered with the governing bodies that controlled altering
sensitive ecological areas and wetlands; 15 years worth to be exact. The
Westport Conservation Commission, The Mass Department of Environmental
Protection, the Army Corp of Engineers, and the Rhode Island Department of
Environmental Management; this multi-state bureaucracy needed to approve the
project. One would defer to another. It was an odyssey. Studies were done to assess
the impact on the wetlands system, and to determine its functions and values. Finally,
in 2001, Ralph turned to expert Scott Rabideau, an environmental consultant, to
help guide the project through the murky waters of the permiting process. The last permit was obtained from
Massachusetts in August of 2006. Ironically, it was the
smallest of fishes that help save the day.
The alewife
is a small herring having a greenish to bluish back and silvery sides with
faint dark stripes. Russ Hart of Westport, then the Fish Commissioner,
had obtained by 1999 two grants for the installation of a new fish ladder to
assist the anadromous alewife in its migration
upstream to spawn. The protected alewife and Westport’s efforts to preserve it softened
resistance and the project was finally allowed to move forward.
As the last
permit was obtained from Massachusetts, Don Lemonde was chosen as the excavator.
Dredging and excavation started immediately to gradually lower the grade of the
pond’s outer perimeter, while deepening the middle finger to support the
habitat of hundreds of unique aquatic species. Along the way Don’s keen eye
spotted many artifacts (some on display today), including a possible fish weir
near the dam that may have been used to catch the herring. Up to 5000 cubic
yards of mud and silt were removed to the Tiverton Landfill.

Above left: 60% of the original pond’s size was
excavated and dredged to provide sufficient capacity to power the mill. Above right: A large filtration bag was
used to “freshen” the deep center pool during
excavation, protecting aquatic life from silt suffocation. Lower left: Laying the foundation of the massive stone wall that
will support the old, crumbling road-side retaining wall. Lower right: 2004 summer photo showing the encroachment of
vegetation in to the pond.
Ralph was
required to retain a prescribed peninsula in the pond a bird sanctuary and
wetlands, and many springs had to be avoided during excavation to protect their
integrity. For now, part of the ramp used to transport machines and mud will
remain in place. In the future look for a possible boat ramp
for canoes and kayaks, and the introduction of salmon into the pond.
Historical footnote: In 1983, the Fish Commissioners
(Daniel P. Sullivan, Edward T. Earle, and John Doherty) were directed to
establish a memorial dedicated to the memory of Albert Rosinha at the Herring
Run at Adamsville Pond. Mr. Rosinha, a fisherman and former Fish Commissioner,
died July 24, 1981. He was injured in a shell-fishing boat accident, and died
shortly thereafter. The project was completed and an appropriate sign was
erected to identify the area in September 1983. (The Albert Rosinha Herring Run) In the same year, work was begun
to repair the ladders of the Albert Rosinha Herring Run. The Fish Commissioners
in conjunction with the Division of Marine Fisheries began restocking Albert
Rosinha Herring Run and completed the work in the spring of 1984. Source:
Town of Westport 1983 Annual Report.

Above left: The rebuilding of the dam’s planking
with 2-inch, tongue and grooved oak boards. Right: A deep pool of water was left in place throughout the
excavation to protect any aquatic life, especially alewife, which may have been
trapped there when the pond was drained.
In late
fall 2007, Don finished work, with the financial support of the Town of
Westport, on a new stone foundation and retaining wall to support the crumbling
road-side dry rock wall. He also completed a “plunge pool”, a rubble-filled
walled enclosure on the southwest corner of the pond next to Adamsville Road
that will filter stormwater run-off before it enters
the pond. Next to the “plunge pool” Don installed a dry hydrant, a deep pit
protected on two sides by a stone wall that will allow for the taking of water
by the area fire departments.

Above left: Don LeMonde.
Center: Thorton
Simmons demonstrating the dam’s new, oak-handled sluice board controls. Right: Adamsville Pond is fully filled
with November 2007 rains.
It is impossible
for this encapsulation of events to fully describe the many years of time and
money spent in research and negotiation to produce the ultimate success of this
restoration project. That’s a story for another day!
Some
funding was obtained from NRCS of the United States Department of Agriculture.
Source: Some information obtained from Jason Ringler,
Wetlands Biologist, Natural Resource Services, Inc.
- - -
End - - -
Community
Events of Westport © 2008 All rights reserved.